PIVOTAL INFRASTRUCTURE PVT LTD
NAME:PIVOTAL INFRASTRUCTURE
F20/100
Poor track record
Tracking 3 projects — 0 delivered, 3 still active. 3 of 3 (100%) ran late.
Delivery breakdown
How this builder's 3 tracked projects are split by outcome.
Key numbers
Total projects
3
Active
3
Completed
0
Delayed
3 (100%)
Late or overdue
Avg delay
—
On finished projects
On-time rate
—
Of completed projects
Extension rate
0%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (3)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
RERA-GRG-420-2019 Gurgaon · HR | Gurgaon HR | 1 Sept 2017 | 29 May 2021 | Overdue | 61 mo overdue |
RERA-GRG-411-2019 Gurgaon · HR | Gurgaon HR | 19 Sept 2017 | 31 Aug 2020 | Overdue | 70 mo overdue |
RERA-PKL-636-2019 Faridabad · HR | Faridabad HR | — | 31 Dec 2020 | Overdue | 66 mo overdue |