PRESTIGE ESTATES PROJECTS LIMITED

RERA delivery track record · complaints · project delays

NAME:PRESTIGE ESTATES PROJECTS

Good track record

Tracking 8 projects — 1 delivered, 7 still active. 6 of 8 (75%) ran late.

Delivery breakdown

How this builder's 8 tracked projects are split by outcome.

1 Delivered on time6 Overdue1 In progress

Key numbers

Total projects

8

Active

7

Completed

1

Delayed

6 (75%)

Late or overdue

Avg delay

0 mo

On finished projects

On-time rate

100%

Of completed projects

Extension rate

0%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (8)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
P51900031285
Mumbai City · MH
Mumbai City
MH
15 Oct 202131 Dec 2025CompletedOn track
P51800031980
Mumbai Suburban · MH
Mumbai Suburban
MH
3 Dec 202131 Dec 2026In progressOn track
PRM/KA/RERA/1251/446/PR/170824/000057
Bengaluru Urban · KA
Bengaluru Urban
KA
24 Aug 201725 Dec 2019Overdue78 mo overdue
PRM/KA/RERA/1251/446/PR/170824/000058
Bengaluru Urban · KA
Bengaluru Urban
KA
24 Aug 201731 Dec 2019Overdue78 mo overdue
PRM/KA/RERA/1251/446/PR/170915/000082
Bengaluru Urban · KA
Bengaluru Urban
KA
15 Sept 201730 Jun 2019Overdue84 mo overdue
PRM/KA/RERA/1251/309/PR/170913/000129
Bengaluru Urban · KA
Bengaluru Urban
KA
13 Sept 201730 Sept 2019Overdue81 mo overdue
PRM/KA/RERA/1251/310/PR/170913/000109
Bengaluru Urban · KA
Bengaluru Urban
KA
13 Sept 201730 Jun 2020Overdue72 mo overdue
PRM/KA/RERA/1251/446/PR/170824/000077
Bengaluru Urban · KA
Bengaluru Urban
KA
24 Aug 201730 Nov 2020Overdue67 mo overdue