PRITHVEELINK BUILDWELL PRIVATE LIMITED

NAME:PRITHVEELINK BUILDWELL PRIVATE LIMITED

Weak track record

Tracking 2 projects — 2 delivered, 0 still active. 1 of 2 (50%) ran late by an average of 3 months. Limited history — read the project list before drawing conclusions.

This builder has only 2 tracked projects in our coverage area, so the grade is based on a small sample. Read the project list below before drawing conclusions.

Delivery breakdown

How this builder's 2 tracked projects are split by outcome.

1 Delivered on time1 Delivered late

Key numbers

Total projects

2

Active

0

Completed

2

Delayed

1 (50%)

Late or overdue

Avg delay

3 mo

Worst: 6 mo

On-time rate

50%

Of completed projects

Extension rate

50%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (2)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
GALAXY ROYALE Ph1 Towers A Keshav/B Gokul/CSC
UPRERAPRJ5806
UP
30 Jul 201731 Mar 2018CompletedOn track
GALAXY ROYALE ,Phase-2(Tower C Vrindavan,Club)
UPRERAPRJ5836
UP
28 Sept 201731 May 2021Completed6 mo delay