PSC PROPERTIES PRIVATE LIMITED

NAME:PSC PROPERTIES PRIVATE LIMITED

Poor track record

Tracking 3 projects — 3 delivered, 0 still active. 2 of 3 (67%) ran late by an average of 6 months.

Delivery breakdown

How this builder's 3 tracked projects are split by outcome.

1 Delivered on time2 Delivered late

Key numbers

Total projects

3

Active

0

Completed

3

Delayed

2 (67%)

Late or overdue

Avg delay

6 mo

Worst: 12 mo

On-time rate

33%

Of completed projects

Extension rate

67%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (3)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
Vighnarajendra
P51800000476
Mumbai Suburban
MH
18 Jul 201731 Dec 2017CompletedOn track
PRAYOG
P51800001932
Mumbai Suburban
MH
29 Jul 201731 Dec 2017Completed12 mo delay
Royal Court - Commercial
P51800002784
Mumbai Suburban
MH
4 Aug 201731 Jul 2018Completed6 mo delay