Rashmi Housing Private Limited
RERA delivery track record · complaints · project delays
NAME:RASHMI HOUSING
F20/100
Poor track record
Tracking 3 projects — 0 delivered, 3 still active. 3 of 3 (100%) ran late.
Delivery breakdown
How this builder's 3 tracked projects are split by outcome.
Key numbers
Total projects
3
Active
3
Completed
0
Delayed
3 (100%)
Late or overdue
Avg delay
—
On finished projects
On-time rate
—
Of completed projects
Extension rate
0%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (3)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
P51800015452 Mumbai Suburban · MH | Mumbai Suburban MH | 27 Feb 2018 | 30 Mar 2023 | Overdue | 39 mo overdue |
P51700007534 Thane · MH | Thane MH | 17 Aug 2017 | 30 Jun 2024 | Overdue | 24 mo overdue |
P51700011990 Thane · MH | Thane MH | 1 Sept 2017 | 30 Jun 2023 | Overdue | 36 mo overdue |