RISHABH ENTERPRISES
NAME:RISHABH ENTERPRISES
A91/100
Strong track record
Tracking 4 projects — 3 delivered, 1 still active. 1 of 4 (25%) ran late.
Delivery breakdown
How this builder's 4 tracked projects are split by outcome.
Key numbers
Total projects
4
Active
1
Completed
3
Delayed
1 (25%)
Late or overdue
Avg delay
0 mo
On finished projects
On-time rate
100%
Of completed projects
Extension rate
0%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (4)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
P51800010107 Mumbai Suburban · MH | Mumbai Suburban MH | 24 Aug 2017 | 30 Dec 2021 | Overdue | 54 mo overdue |
P51800018331 Mumbai Suburban · MH | Mumbai Suburban MH | 23 Oct 2018 | 30 Dec 2025 | Completed | On track |
P51800018350 Mumbai Suburban · MH | Mumbai Suburban MH | 24 Oct 2018 | 30 Dec 2025 | Completed | On track |
P51800026305 Mumbai Suburban · MH | Mumbai Suburban MH | 7 Sept 2020 | 30 Jun 2027 | Completed | On track |