RISHABRAJ ESTATE DEVELOPERS PVT LTD

RERA delivery track record · complaints · project delays

NAME:RISHABRAJ ESTATE DEVELOPERS

Mixed track record

Tracking 8 projects — 5 delivered, 3 still active. 3 of 8 (38%) ran late by an average of 5 months.

Delivery breakdown

How this builder's 8 tracked projects are split by outcome.

3 Delivered on time2 Delivered late1 Overdue2 In progress

Key numbers

Total projects

8

Active

3

Completed

5

Delayed

3 (38%)

Late or overdue

Avg delay

4.8 mo

Worst: 12 mo

On-time rate

60%

Of completed projects

Extension rate

25%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (8)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
P51800007281
Mumbai Suburban · MH
Mumbai Suburban
MH
17 Aug 201731 Dec 2017Completed12 mo delay
P51800027330
Mumbai Suburban · MH
Mumbai Suburban
MH
2 Dec 202030 May 2027In progressOn track
P51800030530
Mumbai Suburban · MH
Mumbai Suburban
MH
30 Aug 202131 Aug 2024CompletedOn track
P51800031075
Mumbai Suburban · MH
Mumbai Suburban
MH
5 Oct 202131 Aug 2024CompletedOn track
P51800033826
Mumbai Suburban · MH
Mumbai Suburban
MH
8 Mar 202231 Dec 2025CompletedOn track
P51800033878
Mumbai Suburban · MH
Mumbai Suburban
MH
14 Mar 202228 Feb 2027In progressOn track
P51800045471
Mumbai Suburban · MH
Mumbai Suburban
MH
19 May 202231 Dec 2025Overdue6 mo overdue
P51800002464
Mumbai Suburban · MH
Mumbai Suburban
MH
1 Aug 201731 Dec 2018Completed12 mo delay