RUBBERWALA HOUSING & INFRASTRUCTURE LTD.

NAME:RUBBERWALA HOUSING & INFRASTRUCTURE LTD.

Mixed track record

Tracking 2 projects — 0 delivered, 2 still active. 1 of 2 (50%) ran late. Limited history — read the project list before drawing conclusions.

This builder has only 2 tracked projects in our coverage area, so the grade is based on a small sample. Read the project list below before drawing conclusions.

Delivery breakdown

How this builder's 2 tracked projects are split by outcome.

1 Overdue1 In progress

Key numbers

Total projects

2

Active

2

Completed

0

Delayed

1 (50%)

Late or overdue

Avg delay

On finished projects

On-time rate

Of completed projects

Extension rate

50%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (2)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
WHITE HOUSE
P51900003831
Mumbai City
MH
6 Aug 201731 Dec 2018Overdue12 mo overdue
THE PLATINUM
P51900007633
Mumbai City
MH
17 Aug 201730 Dec 2026In progressOn track