S.K.DEVELOPERS
RERA delivery track record · complaints · project delays
NAME:S K DEVELOPERS
B75/100
Good track record
Tracking 6 projects — 5 delivered, 1 still active. 1 of 6 (17%) ran late by an average of 5 months.
Delivery breakdown
How this builder's 6 tracked projects are split by outcome.
Key numbers
Total projects
6
Active
1
Completed
5
Delayed
1 (17%)
Late or overdue
Avg delay
4.8 mo
Worst: 24 mo
On-time rate
80%
Of completed projects
Extension rate
17%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (6)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
P52000005424 Raigarh · MH | Raigarh MH | 11 Aug 2017 | 28 Aug 2022 | Completed | On track |
P52000008128 Raigarh · MH | Raigarh MH | 18 Aug 2017 | 28 Aug 2022 | Completed | On track |
P52000006725 Raigarh · MH | Raigarh MH | 16 Aug 2017 | 31 Dec 2019 | Completed | 24 mo delay |
P51800076681 Mumbai Suburban · MH | Mumbai Suburban MH | 20 Jun 2024 | 26 Apr 2029 | In progress | On track |
P51700007961 Thane · MH | Thane MH | 18 Aug 2017 | 31 Mar 2019 | Completed | On track |
P52100002520 Pune · MH | Pune MH | 1 Aug 2017 | 31 Oct 2018 | Completed | On track |