SAI KRUPA DEVELOPERS
RERA delivery track record · complaints · project delays
NAME:SAI KRUPA DEVELOPERS
D49/100
Weak track record
Tracking 5 projects — 3 delivered, 2 still active. 2 of 5 (40%) ran late by an average of 4 months.
Delivery breakdown
How this builder's 5 tracked projects are split by outcome.
Key numbers
Total projects
5
Active
2
Completed
3
Delayed
2 (40%)
Late or overdue
Avg delay
4 mo
Worst: 12 mo
On-time rate
67%
Of completed projects
Extension rate
80%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (5)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
P52000010578 Raigarh · MH | Raigarh MH | 31 Aug 2017 | 31 Dec 2018 | Overdue | 78 mo overdue |
P52000000739 Raigarh · MH | Raigarh MH | 23 Jul 2017 | 1 Aug 2025 | Completed | On track |
P51800010405 Mumbai Suburban · MH | Mumbai Suburban MH | 24 Aug 2017 | 30 Dec 2018 | Completed | 12 mo delay |
P51700009395 Thane · MH | Thane MH | 22 Aug 2017 | 1 Jul 2026 | Completed | On track |
P51800034335 Mumbai Suburban · MH | Mumbai Suburban MH | 4 Apr 2022 | 30 Dec 2025 | In progress | On track |