SANVO RESORTS PVT. LTD.
RERA delivery track record · complaints · project delays
NAME:SANVO RESORTS
A89/100
Strong track record
Tracking 24 projects — 17 delivered, 7 still active. 6 of 24 (25%) ran late.
Delivery breakdown
How this builder's 24 tracked projects are split by outcome.
Key numbers
Total projects
24
Active
7
Completed
17
Delayed
6 (25%)
Late or overdue
Avg delay
0 mo
On finished projects
On-time rate
100%
Of completed projects
Extension rate
13%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (24)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
P52000000502 Raigarh · MH | Raigarh MH | 18 Jul 2017 | 31 Dec 2019 | Completed | On track |
P52000000573 Raigarh · MH | Raigarh MH | 18 Jul 2017 | 31 Dec 2019 | Completed | On track |
P52000000660 Raigarh · MH | Raigarh MH | 19 Jul 2017 | 30 Dec 2023 | Completed | On track |
P52000000661 Raigarh · MH | Raigarh MH | 19 Jul 2017 | 31 Dec 2019 | Completed | On track |
P52000000670 Raigarh · MH | Raigarh MH | 19 Jul 2017 | 30 Dec 2021 | Overdue | 54 mo overdue |
P52000000713 Raigarh · MH | Raigarh MH | 20 Jul 2017 | 30 Jun 2021 | Completed | On track |
P52000001062 Raigarh · MH | Raigarh MH | 25 Jul 2017 | 30 Dec 2022 | Completed | On track |
P52000000547 Raigarh · MH | Raigarh MH | 18 Jul 2017 | 31 Dec 2018 | Completed | On track |
P52000000662 Raigarh · MH | Raigarh MH | 19 Jul 2017 | 30 Dec 2022 | Completed | On track |
P52000000658 Raigarh · MH | Raigarh MH | 19 Jul 2017 | 31 Dec 2018 | Completed | On track |
P52000000472 Raigarh · MH | Raigarh MH | 18 Jul 2017 | 30 Dec 2023 | Completed | On track |
P52000000495 Raigarh · MH | Raigarh MH | 18 Jul 2017 | 30 Dec 2024 | Overdue | 18 mo overdue |
P52000000522 Raigarh · MH | Raigarh MH | 18 Jul 2017 | 30 Dec 2024 | Overdue | 18 mo overdue |
P52000000663 Raigarh · MH | Raigarh MH | 19 Jul 2017 | 30 Dec 2024 | Overdue | 18 mo overdue |
P52000000664 Raigarh · MH | Raigarh MH | 19 Jul 2017 | 30 Dec 2024 | Completed | On track |
P52000000665 Raigarh · MH | Raigarh MH | 19 Jul 2017 | 30 Dec 2022 | Completed | On track |
P52000000666 Raigarh · MH | Raigarh MH | 19 Jul 2017 | 30 Dec 2025 | Overdue | 6 mo overdue |
P52000000667 Raigarh · MH | Raigarh MH | 19 Jul 2017 | 31 Dec 2019 | Completed | On track |
P52000000668 Raigarh · MH | Raigarh MH | 19 Jul 2017 | 30 Dec 2025 | Completed | On track |
P52000000669 Raigarh · MH | Raigarh MH | 19 Jul 2017 | 30 Dec 2023 | Completed | On track |
P52000000671 Raigarh · MH | Raigarh MH | 19 Jul 2017 | 30 Dec 2026 | In progress | On track |
P52000000674 Raigarh · MH | Raigarh MH | 19 Jul 2017 | 30 Dec 2023 | Completed | On track |
P52000000677 Raigarh · MH | Raigarh MH | 19 Jul 2017 | 30 Jun 2021 | Completed | On track |
P52000001047 Raigarh · MH | Raigarh MH | 25 Jul 2017 | 30 Dec 2023 | Overdue | 30 mo overdue |