SAVITA HOMEMAKERS LLP

NAME:SAVITA HOMEMAKERS LLP

Poor track record

Tracking 2 projects — 1 delivered, 1 still active. 1 of 2 (50%) ran late by an average of 12 months. Limited history — read the project list before drawing conclusions.

This builder has only 2 tracked projects in our coverage area, so the grade is based on a small sample. Read the project list below before drawing conclusions.

Delivery breakdown

How this builder's 2 tracked projects are split by outcome.

1 Delivered late1 In progress

Key numbers

Total projects

2

Active

1

Completed

1

Delayed

1 (50%)

Late or overdue

Avg delay

12 mo

Worst: 12 mo

On-time rate

0%

Of completed projects

Extension rate

100%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (2)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
Goldcrest Residency - Phase 2
P51700010579
Thane
MH
31 Aug 201730 Jun 2021In progressOn track
GOLDCREST RESIDENCY - PHASE 1
P51700012365
Thane
MH
1 Sept 201731 Dec 2019Completed12 mo delay