SHIV KRUPA ENTERPRISE

NAME:SHIV KRUPA ENTERPRISE

Mixed track record

Tracking 3 projects — 2 delivered, 1 still active. 1 of 3 (33%) ran late by an average of 6 months.

Delivery breakdown

How this builder's 3 tracked projects are split by outcome.

1 Delivered on time1 Delivered late1 In progress

Key numbers

Total projects

3

Active

1

Completed

2

Delayed

1 (33%)

Late or overdue

Avg delay

6 mo

Worst: 12 mo

On-time rate

50%

Of completed projects

Extension rate

33%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (3)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
P51800003982
Mumbai Suburban · MH
Mumbai Suburban
MH
7 Aug 201731 Mar 2018CompletedOn track
P51800005548
Mumbai Suburban · MH
Mumbai Suburban
MH
11 Aug 201730 Dec 2022Completed12 mo delay
P51800051004
Mumbai Suburban · MH
Mumbai Suburban
MH
19 May 202331 Dec 2029In progressOn track