Shree Developers

RERA delivery track record · complaints · project delays

NAME:SHREE DEVELOPERS

Mixed track record

Tracking 6 projects — 4 delivered, 2 still active. 3 of 6 (50%) ran late by an average of 2 months.

Delivery breakdown

How this builder's 6 tracked projects are split by outcome.

3 Delivered on time1 Delivered late2 Overdue

Key numbers

Total projects

6

Active

2

Completed

4

Delayed

3 (50%)

Late or overdue

Avg delay

1.8 mo

Worst: 7 mo

On-time rate

75%

Of completed projects

Extension rate

33%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (6)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
P51700013083
Thane · MH
Thane
MH
14 Sept 201731 Jan 2020CompletedOn track
P51800006487
Mumbai Suburban · MH
Mumbai Suburban
MH
14 Aug 201731 Dec 2019CompletedOn track
P51800005303
Mumbai Suburban · MH
Mumbai Suburban
MH
11 Aug 201731 Jul 2018Overdue95 mo overdue
P51900020641
Mumbai City · MH
Mumbai City
MH
30 Apr 20191 Sept 2023Overdue34 mo overdue
P52000003239
Raigarh · MH
Raigarh
MH
5 Aug 201731 Dec 2017CompletedOn track
P52100003686
Pune · MH
Pune
MH
6 Aug 201731 Dec 2017Completed7 mo delay