SHREE SIDDHIVINAYAK ENTERPRISES
NAME:SHREE SIDDHIVINAYAK ENTERPRISES
A82/100
Strong track record
Tracking 3 projects — 2 delivered, 1 still active. 1 of 3 (33%) ran late.
Delivery breakdown
How this builder's 3 tracked projects are split by outcome.
Key numbers
Total projects
3
Active
1
Completed
2
Delayed
1 (33%)
Late or overdue
Avg delay
0 mo
On finished projects
On-time rate
100%
Of completed projects
Extension rate
33%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (3)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
| SUDAMA REGENCY BUILDING NO 1, 5 P51700000953 | Thane MH | 25 Jul 2017 | 31 Oct 2018 | Completed | On track |
| SUDAMA REGENCY BUILDING NO 2,3,4 P51700001217 | Thane MH | 27 Jul 2017 | 30 Dec 2023 | Overdue | 18 mo overdue |
| SHREE SIDDHIVINAYAK ENTERPRISES P51700004774 | Thane MH | 9 Aug 2017 | 1 Dec 2018 | Completed | On track |