Shree Siddhivinayak Infrastructure & Realty
NAME:SHREE SIDDHIVINAYAK INFRASTRUCTURE REALTY
F0/100
Poor track record
Tracking 3 projects — 1 delivered, 2 still active. 2 of 3 (67%) ran late by an average of 48 months.
Delivery breakdown
How this builder's 3 tracked projects are split by outcome.
Key numbers
Total projects
3
Active
2
Completed
1
Delayed
2 (67%)
Late or overdue
Avg delay
48 mo
Worst: 48 mo
On-time rate
0%
Of completed projects
Extension rate
100%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (3)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
P51800014328 Mumbai Suburban · MH | Mumbai Suburban MH | 23 Nov 2017 | 31 Dec 2019 | Completed | 48 mo delay |
P51800012513 Mumbai Suburban · MH | Mumbai Suburban MH | 1 Sept 2017 | 30 Dec 2022 | In progress | On track |
P51800013681 Mumbai Suburban · MH | Mumbai Suburban MH | 23 Oct 2017 | 30 Dec 2023 | Overdue | 6 mo overdue |