Shreeji Construction
RERA delivery track record · complaints · project delays
NAME:SHREEJI CONSTRUCTION
F17/100
Poor track record
Tracking 8 projects — 2 delivered, 6 still active. 3 of 8 (38%) ran late by an average of 33 months.
Delivery breakdown
How this builder's 8 tracked projects are split by outcome.
Key numbers
Total projects
8
Active
6
Completed
2
Delayed
3 (38%)
Late or overdue
Avg delay
33 mo
Worst: 42 mo
On-time rate
0%
Of completed projects
Extension rate
50%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (8)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
P51800006923 Mumbai Suburban · MH | Mumbai Suburban MH | 16 Aug 2017 | 30 Jun 2021 | Overdue | 42 mo overdue |
P51800047335 Mumbai Suburban · MH | Mumbai Suburban MH | 19 Oct 2022 | 30 Jun 2026 | In progress | On track |
P51800032149 Mumbai Suburban · MH | Mumbai Suburban MH | 14 Dec 2021 | 31 Dec 2026 | In progress | On track |
P51800054310 Mumbai Suburban · MH | Mumbai Suburban MH | 15 Jan 2024 | 30 Jun 2027 | In progress | On track |
P51800054233 Mumbai Suburban · MH | Mumbai Suburban MH | 9 Jan 2024 | 30 Jun 2028 | In progress | On track |
P51800076989 Mumbai Suburban · MH | Mumbai Suburban MH | 10 Jul 2024 | 31 Jan 2028 | In progress | On track |
P51800003919 Mumbai Suburban · MH | Mumbai Suburban MH | 7 Aug 2017 | 30 Nov 2020 | Completed | 24 mo delay |
P51800004400 Mumbai Suburban · MH | Mumbai Suburban MH | 9 Aug 2017 | 30 Jun 2020 | Completed | 42 mo delay |