Shreeji Construction

RERA delivery track record · complaints · project delays

NAME:SHREEJI CONSTRUCTION

Poor track record

Tracking 8 projects — 2 delivered, 6 still active. 3 of 8 (38%) ran late by an average of 33 months.

Delivery breakdown

How this builder's 8 tracked projects are split by outcome.

2 Delivered late1 Overdue5 In progress

Key numbers

Total projects

8

Active

6

Completed

2

Delayed

3 (38%)

Late or overdue

Avg delay

33 mo

Worst: 42 mo

On-time rate

0%

Of completed projects

Extension rate

50%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (8)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
P51800006923
Mumbai Suburban · MH
Mumbai Suburban
MH
16 Aug 201730 Jun 2021Overdue42 mo overdue
P51800047335
Mumbai Suburban · MH
Mumbai Suburban
MH
19 Oct 202230 Jun 2026In progressOn track
P51800032149
Mumbai Suburban · MH
Mumbai Suburban
MH
14 Dec 202131 Dec 2026In progressOn track
P51800054310
Mumbai Suburban · MH
Mumbai Suburban
MH
15 Jan 202430 Jun 2027In progressOn track
P51800054233
Mumbai Suburban · MH
Mumbai Suburban
MH
9 Jan 202430 Jun 2028In progressOn track
P51800076989
Mumbai Suburban · MH
Mumbai Suburban
MH
10 Jul 202431 Jan 2028In progressOn track
P51800003919
Mumbai Suburban · MH
Mumbai Suburban
MH
7 Aug 201730 Nov 2020Completed24 mo delay
P51800004400
Mumbai Suburban · MH
Mumbai Suburban
MH
9 Aug 201730 Jun 2020Completed42 mo delay