SHREEPATI BUILD INFRA INVESTMENT LIMITED
RERA delivery track record · complaints · project delays
NAME:SHREEPATI BUILD INFRA INVESTMENT
C60/100
Mixed track record
Tracking 3 projects — 0 delivered, 3 still active. 1 of 3 (33%) ran late.
Delivery breakdown
How this builder's 3 tracked projects are split by outcome.
Key numbers
Total projects
3
Active
3
Completed
0
Delayed
1 (33%)
Late or overdue
Avg delay
—
On finished projects
On-time rate
—
Of completed projects
Extension rate
67%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (3)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
P51900000558 Mumbai City · MH | Mumbai City MH | 18 Jul 2017 | 31 Dec 2019 | Overdue | 42 mo overdue |
P51900000623 Mumbai City · MH | Mumbai City MH | 18 Jul 2017 | 30 Dec 2019 | In progress | On track |
P51900010019 Mumbai City · MH | Mumbai City MH | 23 Aug 2017 | 30 Dec 2026 | In progress | On track |