SUPERTECH LIMITED
NAME:SUPERTECH LIMITED
F19/100
Poor track record
Tracking 25 projects — 12 delivered, 13 still active. 21 of 25 (84%) ran late by an average of 5 months.
Delivery breakdown
How this builder's 25 tracked projects are split by outcome.
Key numbers
Total projects
25
Active
13
Completed
12
Delayed
21 (84%)
Late or overdue
Avg delay
5 mo
Worst: 17.9 mo
On-time rate
33%
Of completed projects
Extension rate
72%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (25)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
| Supertech Czar UPRERAPRJ9414 | Gautam Buddha Nagar UP | 11 Aug 2017 | 30 Dec 2018 | Overdue | 90 mo overdue |
| SUPERTECH ECO VILLAGE-I (PHASE-II) UPRERAPRJ4830 | UP | 9 Aug 2017 | 30 May 2019 | Completed | 6 mo delay |
| ECO VILLAGE-II (PHASE-I) UPRERAPRJ4112 | UP | 4 Aug 2017 | 30 Mar 2018 | Completed | 6 mo delay |
| Supertech Upcountry GH-01 Phase-02 UPRERAPRJ8249 | UP | 9 Aug 2017 | 30 Jun 2019 | Completed | 18 mo delay |
| Supertech Upcountry (Plotted) UPRERAPRJ8267 | UP | 14 Aug 2017 | 30 Dec 2017 | Completed | On track |
| SPORTS VILLAGE (PHASE-II, VILLA) UPRERAPRJ565 | Gautam Buddha Nagar UP | 4 Aug 2017 | 31 Dec 2020 | Overdue | 60 mo overdue |
| SPORTS VILLAGE (PHASE-III, Commercial) UPRERAPRJ650295 | Gautam Buddha Nagar UP | 29 May 2019 | 31 Dec 2022 | Overdue | 36 mo overdue |
| Supertech Eco Village-3 Phase-3 UPRERAPRJ8319 | UP | 8 Aug 2017 | 31 May 2021 | Completed | 6 mo delay |
| SUPERTECH CAPETOWN (PHASE-I) UPRERAPRJ5017 | Gautam Buddha Nagar UP | 10 Aug 2017 | 30 Dec 2019 | Overdue | 78 mo overdue |
| SUPERTECH ECO VILLAGE-III (PHASE-I) UPRERAPRJ604 | UP | 8 Aug 2017 | 31 Mar 2019 | Completed | On track |
| SUPERTECH ECO VILLAGE-I (PHASE-I) UPRERAPRJ4318 | Gautam Buddha Nagar UP | 4 Aug 2017 | 30 Mar 2018 | Overdue | 93 mo overdue |
| SUPERTECH ECO VILLAGE-I PHASE I-C UPRERAPRJ8334 | UP | 9 Aug 2017 | 30 Dec 2017 | Completed | On track |
| SUPERTECH ECO VILLAGE-III (PHASE-II) UPRERAPRJ4714 | Gautam Buddha Nagar UP | 8 Aug 2017 | 31 Dec 2019 | Overdue | 78 mo overdue |
| SUPERTECH ECO VILLAGE-I (PHASE-III) UPRERAPRJ4878 | UP | 9 Aug 2017 | 30 Jul 2022 | Completed | 6 mo delay |
| SUPERTECH ECO VILLAGE-II (PHASE-II) UPRERAPRJ4917 | Gautam Buddha Nagar UP | 10 Aug 2017 | 30 Oct 2019 | Overdue | 62 mo overdue |
| SUPERTECH ECO VILLAGE-II (PHASE-III) UPRERAPRJ4939 | Gautam Buddha Nagar UP | 10 Aug 2017 | 28 Feb 2021 | Overdue | 58 mo overdue |
| SUPERTECH ECO VILLAGE-II (PHASE-IV) UPRERAPRJ4968 | Gautam Buddha Nagar UP | 10 Aug 2017 | 30 Dec 2022 | Overdue | 36 mo overdue |
| SUPERTECH ECO VILLAGE-II PHASE I-C UPRERAPRJ8337 | UP | 9 Aug 2017 | 30 Dec 2017 | Completed | On track |
| SUPERTECH ECOCITI - PHASE-1 UPRERAPRJ9744 | Gautam Buddha Nagar UP | 12 Aug 2017 | 30 Dec 2017 | Overdue | 96 mo overdue |
| SUPERTECH NORTHEYE (PHASE-II) UPRERAPRJ5539 | Gautam Buddha Nagar UP | 10 Aug 2017 | 30 Dec 2020 | Overdue | 60 mo overdue |
| SUPERTECH ORB-R (PHASE-III) UPRERAPRJ5551 | Gautam Buddha Nagar UP | 11 Aug 2017 | 30 Jun 2021 | Overdue | 54 mo overdue |
| SUPERTECH UPCOUNTRY GH-01 (PHASE-I) UPRERAPRJ5582 | Gautam Buddha Nagar UP | 8 Aug 2017 | 30 Jun 2020 | Overdue | 54 mo overdue |
| Supertech Upcountry GH-02 Phase-01 UPRERAPRJ8263 | UP | 8 Aug 2017 | 30 Jun 2019 | Completed | 6 mo delay |
| Emerald Court Phase II (Apex & Ceyane) - Demolished as per the order of Hon'ble Superme Court UPRERAPRJ11486 | UP | 15 Aug 2017 | 1 Jun 2021 | Completed | 6 mo delay |
| SPORTS VILLAGE (PHASE-I) UPRERAPRJ408 | UP | 11 Aug 2017 | 31 Dec 2020 | Completed | 6 mo delay |