Sabari Developers LLP

NAME:Sabari Developers LLP

Poor track record

Tracking 5 projects — 5 delivered, 0 still active. 3 of 5 (60%) ran late by an average of 9 months.

Delivery breakdown

How this builder's 5 tracked projects are split by outcome.

2 Delivered on time3 Delivered late

Key numbers

Total projects

5

Active

0

Completed

5

Delayed

3 (60%)

Late or overdue

Avg delay

9.2 mo

Worst: 17 mo

On-time rate

40%

Of completed projects

Extension rate

60%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (5)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
Sabari Palm View
P51800001155
Mumbai Suburban
MH
26 Jul 201731 Mar 2019CompletedOn track
SABARI HORIZON
P51800003677
Mumbai Suburban
MH
6 Aug 201731 May 2019Completed17 mo delay
NATEKAR HEIGHTS
P51800002547
Mumbai Suburban
MH
1 Aug 201731 May 2019Completed17 mo delay
SABARI HILLGRANGE
P51800007070
Mumbai Suburban
MH
17 Aug 201731 May 2019CompletedOn track
SABARI SHOBHA
P51800003844
Mumbai Suburban
MH
6 Aug 201730 Nov 2020Completed12 mo delay