Sheltrex Karjat Pvt. Ltd.

NAME:Sheltrex Karjat Pvt. Ltd.

Poor track record

Tracking 7 projects — 0 delivered, 7 still active. 7 of 7 (100%) ran late.

Delivery breakdown

How this builder's 7 tracked projects are split by outcome.

7 Overdue

Key numbers

Total projects

7

Active

7

Completed

0

Delayed

7 (100%)

Late or overdue

Avg delay

On finished projects

On-time rate

Of completed projects

Extension rate

0%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (7)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
Sheltrex Smart Phone City Project 1 - Phase IV
P52000007063
Raigarh
MH
17 Aug 201730 Dec 2021Overdue54 mo overdue
Sheltrex Smart Phone City Project 1 - Phase III
P52000004186
Raigarh
MH
8 Aug 201730 Dec 2021Overdue54 mo overdue
Sheltrex Smart Phone City Project 1 - Phase II
P52000012196
Raigarh
MH
1 Sept 201730 Dec 2021Overdue54 mo overdue
Sheltrex Smart Phone City Project 1- Phase V
P52000010525
Raigarh
MH
31 Aug 201730 Dec 2021Overdue54 mo overdue
Sheltrex Smart Phone city Project 1- Phase VI
P52000008685
Raigarh
MH
19 Aug 201730 Dec 2021Overdue54 mo overdue
Sheltrex Smart Phone City Project 2 - Phase II
P51800012221
Raigarh
MH
1 Sept 201730 Dec 2023Overdue30 mo overdue
Sheltrex Smart Phone City Project 2 - Phase I
P51800012307
Raigarh
MH
1 Sept 201730 Dec 2022Overdue42 mo overdue