Shibam Associates

NAME:Shibam Associates

Mixed track record

Tracking 3 projects — 3 delivered, 0 still active. 1 of 3 (33%) ran late by an average of 4 months.

Delivery breakdown

How this builder's 3 tracked projects are split by outcome.

2 Delivered on time1 Delivered late

Key numbers

Total projects

3

Active

0

Completed

3

Delayed

1 (33%)

Late or overdue

Avg delay

4 mo

Worst: 12 mo

On-time rate

67%

Of completed projects

Extension rate

33%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (3)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
Cluster C
P52000006617
Raigarh
MH
14 Aug 201722 Nov 2019Completed12 mo delay
Cluster F
P52000008779
Raigarh
MH
19 Aug 201715 Mar 2019CompletedOn track
Cluster G
P52000009953
Raigarh
MH
23 Aug 201714 May 2022CompletedOn track