THARWANI CONSTRUCTIONS PVT LTD

NAME:THARWANI CONSTRUCTIONS PVT LTD

Poor track record

Tracking 2 projects — 1 delivered, 1 still active. 2 of 2 (100%) ran late by an average of 13 months. Limited history — read the project list before drawing conclusions.

This builder has only 2 tracked projects in our coverage area, so the grade is based on a small sample. Read the project list below before drawing conclusions.

Delivery breakdown

How this builder's 2 tracked projects are split by outcome.

1 Delivered late1 Overdue

Key numbers

Total projects

2

Active

1

Completed

1

Delayed

2 (100%)

Late or overdue

Avg delay

13 mo

Worst: 13 mo

On-time rate

0%

Of completed projects

Extension rate

100%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (2)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
THARWANIS MEGHNA MONTANA PHASE - I
P51700004242
Thane
MH
9 Aug 201730 Jun 2018Completed13 mo delay
THARWANIS MEGHNA MONTANA PHASE - 2
P51700008088
Thane
MH
18 Aug 201730 Dec 2020Overdue22 mo overdue