UMIYA ENTERPRISES
NAME:UMIYA ENTERPRISES
D37/100
Weak track record
Tracking 2 projects — 2 delivered, 0 still active. 1 of 2 (50%) ran late by an average of 9 months. Limited history — read the project list before drawing conclusions.
This builder has only 2 tracked projects in our coverage area, so the grade is based on a small sample. Read the project list below before drawing conclusions.
Delivery breakdown
How this builder's 2 tracked projects are split by outcome.
Key numbers
Total projects
2
Active
0
Completed
2
Delayed
1 (50%)
Late or overdue
Avg delay
9 mo
Worst: 18 mo
On-time rate
50%
Of completed projects
Extension rate
50%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (2)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
| SHIVAM COMPLEX WING D AND E P51700005023 | Thane MH | 9 Aug 2017 | 30 Sept 2018 | Completed | On track |
| UMA GALAXY P51700002937 | Thane MH | 4 Aug 2017 | 30 Jun 2021 | Completed | 18 mo delay |