Uma Enterprises

NAME:Uma Enterprises

Weak track record

Tracking 2 projects — 2 delivered, 0 still active. 1 of 2 (50%) ran late by an average of 6 months. Limited history — read the project list before drawing conclusions.

This builder has only 2 tracked projects in our coverage area, so the grade is based on a small sample. Read the project list below before drawing conclusions.

Delivery breakdown

How this builder's 2 tracked projects are split by outcome.

1 Delivered on time1 Delivered late

Key numbers

Total projects

2

Active

0

Completed

2

Delayed

1 (50%)

Late or overdue

Avg delay

6 mo

Worst: 12 mo

On-time rate

50%

Of completed projects

Extension rate

50%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (2)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
Rosa Oasis Phase 2
P51700005311
Thane
MH
11 Aug 201731 Dec 2018Completed12 mo delay
Rosa Oasis Phase 3
P51700006155
Thane
MH
14 Aug 201731 Dec 2017CompletedOn track