VARDHMAN DEVELOPERS LTD

RERA delivery track record · complaints · project delays

NAME:VARDHMAN DEVELOPERS

Poor track record

Tracking 4 projects — 1 delivered, 3 still active. 3 of 4 (75%) ran late by an average of 24 months.

Delivery breakdown

How this builder's 4 tracked projects are split by outcome.

1 Delivered late2 Overdue1 In progress

Key numbers

Total projects

4

Active

3

Completed

1

Delayed

3 (75%)

Late or overdue

Avg delay

24 mo

Worst: 24 mo

On-time rate

0%

Of completed projects

Extension rate

100%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (4)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
P51800006315
Mumbai Suburban · MH
Mumbai Suburban
MH
14 Aug 201731 Dec 2018Completed24 mo delay
P51900008829
Mumbai City · MH
Mumbai City
MH
19 Aug 201730 Dec 2023In progressOn track
P51800032084
Mumbai Suburban · MH
Mumbai Suburban
MH
6 Dec 202131 Dec 2024Overdue6 mo overdue
P51800005952
Mumbai Suburban · MH
Mumbai Suburban
MH
14 Aug 201730 Dec 2019Overdue15 mo overdue