Poor track record
Tracking 3 projects — 1 delivered, 2 still active. 2 of 3 (67%) ran late by an average of 24 months.
Delivery breakdown
How this builder's 3 tracked projects are split by outcome.
Key numbers
Total projects
3
Active
2
Completed
1
Delayed
2 (67%)
Late or overdue
Avg delay
24 mo
Worst: 24 mo
On-time rate
0%
Of completed projects
Extension rate
100%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (3)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
| VARDHMAN GRANDEUR P51800005952 | Mumbai Suburban MH | 14 Aug 2017 | 30 Dec 2019 | Overdue | 15 mo overdue |
| VARDHMAN EMPIRE P51800006315 | Mumbai Suburban MH | 14 Aug 2017 | 31 Dec 2018 | Completed | 24 mo delay |
| VARDHMAN FLORA PHASE I P51900008829 | Mumbai City MH | 19 Aug 2017 | 30 Dec 2023 | In progress | On track |