VINOD PREMCHAND CHANDWANI
NAME:VINOD PREMCHAND CHANDWANI
A82/100
Strong track record
Tracking 7 projects — 7 delivered, 0 still active. 1 of 7 (14%) ran late by an average of 3 months.
Delivery breakdown
How this builder's 7 tracked projects are split by outcome.
Key numbers
Total projects
7
Active
0
Completed
7
Delayed
1 (14%)
Late or overdue
Avg delay
2.6 mo
Worst: 18 mo
On-time rate
86%
Of completed projects
Extension rate
14%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (7)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
P52100000191 Pune · MH | Pune MH | 10 Jul 2017 | 30 Jun 2019 | Completed | On track |
P52100000173 Pune · MH | Pune MH | 10 Jul 2017 | 13 Dec 2020 | Completed | On track |
P52100000276 Pune · MH | Pune MH | 12 Jul 2017 | 31 Dec 2019 | Completed | On track |
P52100000386 Pune · MH | Pune MH | 15 Jul 2017 | 30 Dec 2021 | Completed | On track |
P52100000194 Pune · MH | Pune MH | 10 Jul 2017 | 30 Nov 2020 | Completed | On track |
P52100000330 Pune · MH | Pune MH | 15 Jul 2017 | 30 Jun 2019 | Completed | 18 mo delay |
P52100001188 Pune · MH | Pune MH | 27 Jul 2017 | 31 Jul 2019 | Completed | On track |