Tracking 3 projects — 2 delivered, 1 still active. No delays recorded so far.
Delivery breakdown
How this builder's 3 tracked projects are split by outcome.
Key numbers
Total projects
3
Active
1
Completed
2
Delayed
0 (0%)
Late or overdue
Avg delay
0 mo
On finished projects
On-time rate
100%
Of completed projects
Extension rate
0%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (3)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
| Runwal Forests Tower 9 - 11 P51800001137 | Mumbai Suburban MH | 26 Jul 2017 | 30 Jun 2026 | In progress | On track |
| Runwal Forests Tower 5-8 P51800001838 | Mumbai Suburban MH | 29 Jul 2017 | 30 Dec 2022 | Completed | On track |
| Runwal Forest Tower 1-4 P51800000818 | Mumbai Suburban MH | 23 Jul 2017 | 30 Apr 2022 | Completed | On track |