yashraj corporation

NAME:yashraj corporation

Poor track record

Tracking 2 projects — 1 delivered, 1 still active. 2 of 2 (100%) ran late by an average of 27 months. Limited history — read the project list before drawing conclusions.

This builder has only 2 tracked projects in our coverage area, so the grade is based on a small sample. Read the project list below before drawing conclusions.

Delivery breakdown

How this builder's 2 tracked projects are split by outcome.

1 Delivered late1 Overdue

Key numbers

Total projects

2

Active

1

Completed

1

Delayed

2 (100%)

Late or overdue

Avg delay

27 mo

Worst: 27 mo

On-time rate

0%

Of completed projects

Extension rate

100%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (2)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
Moreshwar tower
P51800003786
Mumbai Suburban
MH
6 Aug 201731 Mar 2020Completed27 mo delay
DEVDATTA TOWER
P51800004163
Mumbai Suburban
MH
8 Aug 201730 Nov 2020Overdue33 mo overdue