E HOMES INFRASTRUCTURE PVT LTD
UPRERAPRM10154
D45/100
Weak track record
Tracking 4 projects — 0 delivered, 4 still active. 2 of 4 (50%) ran late.
Delivery breakdown
How this builder's 4 tracked projects are split by outcome.
Key numbers
Total projects
4
Active
4
Completed
0
Delayed
2 (50%)
Late or overdue
Avg delay
—
On finished projects
On-time rate
—
Of completed projects
Extension rate
75%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (4)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
| The Jewel of Noida (Phase I) UPRERAPRJ4327 | Gautam Buddha Nagar UP | 29 Jul 2017 | 1 Dec 2018 | Overdue | 91 mo overdue |
| The Jewel of Noida (Phase II) UPRERAPRJ4350 | Gautam Buddha Nagar UP | 29 Jul 2017 | 1 Dec 2022 | Overdue | 37 mo overdue |
| The Jewel of Noida (Phase III) - Burj Noida UPRERAPRJ498423 | Gautam Buddha Nagar UP | 15 Feb 2019 | 4 Nov 2028 | In progress | On track |
| The Jewel of Noida (Phase IV) - Avenues at Burj Noida UPRERAPRJ936659 | Gautam Buddha Nagar UP | 2 Feb 2019 | 4 Nov 2028 | In progress | On track |