← Back to search

TRIDENT INFRA HOMES PVT. LTD.

UPRERAPRM1568

Poor track record

Tracking 3 projects — 0 delivered, 3 still active. 3 of 3 (100%) ran late.

Delivery breakdown

How this builder's 3 tracked projects are split by outcome.

3 Overdue

Key numbers

Total projects

3

Active

3

Completed

0

Delayed

3 (100%)

Late or overdue

Avg delay

On finished projects

On-time rate

Of completed projects

Extension rate

33%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (3)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
Trident Embassy Phase-3 (Towers J,K,L & Comm)
UPRERAPRJ6492
Gautam Buddha Nagar
UP
31 Jul 201731 Dec 2021Overdue53 mo overdue
Trident Embassy Phase-1 (TOWERS A,B,C,D,E,F)
UPRERAPRJ6457
Gautam Buddha Nagar
UP
31 Jul 201731 Mar 2018Overdue99 mo overdue
Trident Embassy Phase-2 (Towers G,H, I)
UPRERAPRJ6476
Gautam Buddha Nagar
UP
31 Jul 201731 Dec 2018Overdue90 mo overdue