MARATHON NEXWORLD ELARA-1
P51700000478
Behind schedule
This project is about 24 months past its latest deadline and is not yet marked completed.
Where this project stands
The journey from RERA registration to completion, in order.
Past deadline by ~24 months.
Registered with RERA
18 Jul 2017Original promised completion
30 Jun 2023The deadline the builder committed to at registration.
Revised deadline after extensions
29 Jun 2024Pushed back ~12 months across 1 extension.
Today — still not completed
About 24 months past the latest deadline.
Timeline & delay
Key dates and how they compare to what was promised.
18 Jul 2017
When the project was registered with RERA.
30 Jun 2023
The deadline committed to at registration.
29 Jun 2024
After all approved extensions.
—
Handover date, when available.
24 mo overdue23.8 mo
How far past deadline an ongoing project is.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
6
Complaints against the builder
0
Often reported per project on MahaRERA
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 30 Jun 2023 | 29 Jun 2024 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 4 projects — 2 delivered, 2 still active. 4 of 4 (100%) ran late by an average of 12 months.
See MATRIX ENCLAVES PROJECTS DEV. PVT. LTD's full track record →
Official records
Builder: MATRIX ENCLAVES PROJECTS DEV. PVT. LTD (NAME:MATRIX ENCLAVES PROJECTS DEV. PVT. LTD)