MARATHON NEXWORLD AURA-1
P51700000652
Delivered — but late
This project was completed about 12 months after its original promised deadline.
Where this project stands
The journey from RERA registration to completion, in order.
Completed.
Registered with RERA
19 Jul 2017Original promised completion
30 Dec 2022The deadline the builder committed to at registration.
Revised deadline after extensions
29 Dec 2023Pushed back ~12 months across 1 extension.
Marked completed on the portal
Shown as completed on the official registry (no exact date scraped).
Timeline & delay
Key dates and how they compare to what was promised.
19 Jul 2017
When the project was registered with RERA.
30 Dec 2022
The deadline committed to at registration.
29 Dec 2023
After all approved extensions.
—
Handover date, when available.
12 mo delay12 mo
How late the finished project was.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
30
Complaints against the builder
0
Often reported per project on MahaRERA
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 30 Dec 2022 | 29 Dec 2023 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 4 projects — 2 delivered, 2 still active. 4 of 4 (100%) ran late by an average of 12 months.
See MATRIX ENCLAVES PROJECTS DEV. PVT. LTD's full track record →
Official records
Builder: MATRIX ENCLAVES PROJECTS DEV. PVT. LTD (NAME:MATRIX ENCLAVES PROJECTS DEV. PVT. LTD)
Data last refreshed 21 Jun 2026.