RUNWAL GARDEN CITY - DAHLIA
P51700001095
Delivered — but late
This project was completed about 66 months after its original promised deadline.
Where this project stands
The journey from RERA registration to completion, in order.
Completed.
Registered with RERA
26 Jul 2017Original promised completion
30 Jun 2018The deadline the builder committed to at registration.
Revised deadline after extensions
31 Dec 2023Pushed back ~66 months across 1 extension.
Marked completed on the portal
Shown as completed on the official registry (no exact date scraped).
Timeline & delay
Key dates and how they compare to what was promised.
26 Jul 2017
When the project was registered with RERA.
30 Jun 2018
The deadline committed to at registration.
31 Dec 2023
After all approved extensions.
—
Handover date, when available.
66 mo delay66 mo
How late the finished project was.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
2
Complaints against the builder
0
Often reported per project on MahaRERA
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 30 Jun 2018 | 31 Dec 2023 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Weak track record
Tracking 3 projects — 2 delivered, 1 still active. 1 of 3 (33%) ran late by an average of 33 months.
Official records
Builder: RUNWAL DEVELOPERS LIMITED (NAME:RUNWAL DEVELOPERS LIMITED)
Data last refreshed 21 Jun 2026.