BALAJI AURA
P51700003428
Delivered — but late
This project was completed about 23 months after its original promised deadline.
Where this project stands
The journey from RERA registration to completion, in order.
Completed.
Registered with RERA
5 Aug 2017Original promised completion
30 Sept 2022The deadline the builder committed to at registration.
Revised deadline after extensions
30 Aug 2024Pushed back ~23 months across 1 extension.
Marked completed on the portal
Shown as completed on the official registry (no exact date scraped).
Timeline & delay
Key dates and how they compare to what was promised.
5 Aug 2017
When the project was registered with RERA.
30 Sept 2022
The deadline committed to at registration.
30 Aug 2024
After all approved extensions.
—
Handover date, when available.
23 mo delay23 mo
How late the finished project was.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
1
Complaints against the builder
0
Often reported per project on MahaRERA
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 30 Sept 2022 | 30 Aug 2024 | MahaRERA extension (original vs revised completion date) |