Windson Heights
P51700003576
Under construction
Currently within its planned build window. Watch the deadline and any new extensions.
Where this project stands
The journey from RERA registration to completion, in order.
Within the planned build window.
Registered with RERA
5 Aug 2017Original promised completion
30 Dec 2023The deadline the builder committed to at registration.
Revised deadline after extensions
31 Dec 2028Pushed back ~60 months across 1 extension.
Today — in progress
About 30 months left until the deadline.
Timeline & delay
Key dates and how they compare to what was promised.
5 Aug 2017
When the project was registered with RERA.
30 Dec 2023
The deadline committed to at registration.
31 Dec 2028
After all approved extensions.
—
Handover date, when available.
On track0 mo
How far past deadline an ongoing project is.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
1
Complaints against the builder
0
Often reported per project on MahaRERA
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 30 Dec 2023 | 31 Dec 2028 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Strong track record
Tracking 1 project — 0 delivered, 1 still active. Limited history — read the project list before drawing conclusions.
See Ovla Builders & Developers Pvt. Ltd.'s full track record →
Official records
Builder: Ovla Builders & Developers Pvt. Ltd. (NAME:Ovla Builders & Developers Pvt. Ltd.)
Data last refreshed 21 Jun 2026.