P51700003805

Thane, MaharashtraOthersCompleted

Delivered — but late

This project was completed about 30 months after its original promised deadline.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 6 Aug 2017Due 29 Dec 2023

Completed.

  1. Registered with RERA

    6 Aug 2017
  2. Original promised completion

    30 Jun 2021

    The deadline the builder committed to at registration.

  3. Revised deadline after extensions

    29 Dec 2023

    Pushed back ~30 months across 1 extension.

  4. Marked completed on the portal

    Shown as completed on the official registry (no exact date scraped).

Timeline & delay

Key dates and how they compare to what was promised.

6 Aug 2017

When the project was registered with RERA.

30 Jun 2021

The deadline committed to at registration.

29 Dec 2023

After all approved extensions.

Handover date, when available.

30 mo delay30 mo

How late the finished project was.

1

More extensions can signal execution risk.

On MahaRERA this project's registration status is Ongoing and its completion status is Completed. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

Often reported per project on MahaRERA

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
30 Jun 202129 Dec 2023MahaRERA extension (original vs revised completion date)

About the builder

How this developer has performed across all their tracked projects.

Poor track record

Tracking 1 project — 1 delivered, 0 still active. 1 of 1 (100%) ran late by an average of 30 months. Limited history — read the project list before drawing conclusions.

1 projects1 delayed (100%)0% on time

See CONCEPT REALTY's full track record →

Official records

View this project on the MahaRERA portal

Builder: CONCEPT REALTY (NAME:CONCEPT REALTY)

Data last refreshed 21 Jun 2026.