USHA KIRAN RESIDENCY F1 F2

RERA project status · delays · complaints

P51700004142

Thane, MaharashtraOthersOverdue

Behind schedule

This project is past its latest deadline and is not yet marked completed.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 8 Aug 2017Due 31 Jul 2026

Past deadline by ~0 months.

  1. Registered with RERA

    8 Aug 2017
  2. Original promised completion

    31 Dec 2018

    The deadline the builder committed to at registration.

  3. Revised deadline after extensions

    31 Jul 2026

    Pushed back ~91 months across 1 extension.

  4. Today — still not completed

    About 0 months past the latest deadline.

Timeline & delay

Key dates and how they compare to what was promised.

8 Aug 2017

When the project was registered with RERA.

31 Dec 2018

The deadline committed to at registration.

31 Jul 2026

After all approved extensions.

Handover date, when available.

On track0 mo

How far past deadline an ongoing project is.

1

More extensions can signal execution risk.

On MahaRERA this project's registration status is Ongoing and its completion status is Active. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

Often reported per project on MahaRERA

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
31 Dec 201831 Jul 2026MahaRERA extension (original vs revised completion date)

Official records

View this project on the MahaRERA portal

Data last refreshed 23 Jun 2026.