Registered 9 Aug 2017Due 30 Jun 2026

Approaching the deadline.

  1. Registered with RERA

    9 Aug 2017
  2. Original promised completion

    30 Dec 2023

    The deadline the builder committed to at registration.

  3. Revised deadline after extensions

    30 Jun 2026

    Pushed back ~30 months across 1 extension.

  4. Today — in progress

    Deadline is near.

Timeline & delay

Key dates and how they compare to what was promised.

9 Aug 2017

When the project was registered with RERA.

30 Dec 2023

The deadline committed to at registration.

30 Jun 2026

After all approved extensions.

Handover date, when available.

On track0 mo

How far past deadline an ongoing project is.

1

More extensions can signal execution risk.

On MahaRERA this project's registration status is Ongoing and its completion status is Active. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

1

Complaints against the builder

0

Often reported per project on MahaRERA

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
30 Dec 202330 Jun 2026MahaRERA extension (original vs revised completion date)

About the builder

How this developer has performed across all their tracked projects.

Mixed track record

Tracking 4 projects — 0 delivered, 4 still active. 1 of 4 (25%) ran late.

4 projects1 delayed (25%)

See Ravi Developments's full track record →

Official records

View this project on the MahaRERA portal

Builder: Ravi Developments (NAME:Ravi Developments)

Data last refreshed 21 Jun 2026.