Lifestyle City Kalyan- Platano A
P51700005583
Delivered — but late
This project was completed about 49 months after its original promised deadline.
Where this project stands
The journey from RERA registration to completion, in order.
Completed.
Registered with RERA
11 Aug 2017Original promised completion
31 Dec 2018The deadline the builder committed to at registration.
Revised deadline after extensions
30 Jan 2023Pushed back ~49 months across 1 extension.
Marked completed on the portal
Shown as completed on the official registry (no exact date scraped).
Timeline & delay
Key dates and how they compare to what was promised.
11 Aug 2017
When the project was registered with RERA.
31 Dec 2018
The deadline committed to at registration.
30 Jan 2023
After all approved extensions.
—
Handover date, when available.
49 mo delay49 mo
How late the finished project was.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
51
Complaints against the builder
0
Often reported per project on MahaRERA
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 31 Dec 2018 | 30 Jan 2023 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 27 projects — 8 delivered, 19 still active. 27 of 27 (100%) ran late by an average of 41 months.
See Nirmal Lifestyle (Kalyan) Private Limited's full track record →
Official records
Builder: Nirmal Lifestyle (Kalyan) Private Limited (NAME:Nirmal Lifestyle (Kalyan) Private Limited)
Data last refreshed 21 Jun 2026.