PARKWOODS D5
P51700007024
Under construction
Currently within its planned build window. Watch the deadline and any new extensions.
Where this project stands
The journey from RERA registration to completion, in order.
Approaching the deadline.
Registered with RERA
17 Aug 2017Original promised completion
30 Mar 2026The deadline the builder committed to at registration.
Revised deadline after extensions
31 Dec 2026Pushed back ~9 months across 1 extension.
Today — in progress
About 6 months left until the deadline.
Timeline & delay
Key dates and how they compare to what was promised.
17 Aug 2017
When the project was registered with RERA.
30 Mar 2026
The deadline committed to at registration.
31 Dec 2026
After all approved extensions.
—
Handover date, when available.
On track0 mo
How far past deadline an ongoing project is.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
2
Complaints against the builder
0
Often reported per project on MahaRERA
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 30 Mar 2026 | 31 Dec 2026 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Strong track record
Tracking 2 projects — 1 delivered, 1 still active. No delays recorded so far. Limited history — read the project list before drawing conclusions.
See Aniline Construction Company Private Limited's full track record →
Official records
Builder: Aniline Construction Company Private Limited (NAME:Aniline Construction Company Private Limited)
Data last refreshed 21 Jun 2026.