← Back to search

Regency Antilia Phase - III

P51700008116

Thane, MaharashtraOthersCompleted

Delivered — but late

This project was completed about 18 months after its original promised deadline.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 18 Aug 2017Due 29 Dec 2020

Completed.

  1. Registered with RERA

    18 Aug 2017
  2. Original promised completion

    30 Jun 2019

    The deadline the builder committed to at registration.

  3. Revised deadline after extensions

    29 Dec 2020

    Pushed back ~18 months across 1 extension.

  4. Marked completed on the portal

    Shown as completed on the official registry (no exact date scraped).

Timeline & delay

Key dates and how they compare to what was promised.

18 Aug 2017

When the project was registered with RERA.

30 Jun 2019

The deadline committed to at registration.

29 Dec 2020

After all approved extensions.

Handover date, when available.

18 mo delay18 mo

How late the finished project was.

1

More extensions can signal execution risk.

On MahaRERA this project's registration status is Ongoing and its completion status is Completed. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

Often reported per project on MahaRERA

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
30 Jun 201929 Dec 2020MahaRERA extension (original vs revised completion date)

About the builder

How this developer has performed across all their tracked projects.

Weak track record

Tracking 6 projects — 6 delivered, 0 still active. 3 of 6 (50%) ran late by an average of 5 months.

6 projects3 delayed (50%)50% on time

See REGENCY NIRMAN LTD's full track record →

Official records

View this project on the MahaRERA portal

Builder: REGENCY NIRMAN LTD (NAME:REGENCY NIRMAN LTD)

Data last refreshed 21 Jun 2026.