BLDG 23 AS PER SALE PLAN WING E AS PER APPROVED PLAN
P51700008895
Under construction
Currently within its planned build window. Watch the deadline and any new extensions.
Where this project stands
The journey from RERA registration to completion, in order.
Approaching the deadline.
Registered with RERA
19 Aug 2017Original promised completion
30 Dec 2023The deadline the builder committed to at registration.
Revised deadline after extensions
30 Dec 2027Pushed back ~48 months across 1 extension.
Today — in progress
About 18 months left until the deadline.
Timeline & delay
Key dates and how they compare to what was promised.
19 Aug 2017
When the project was registered with RERA.
30 Dec 2023
The deadline committed to at registration.
30 Dec 2027
After all approved extensions.
—
Handover date, when available.
On track0 mo
How far past deadline an ongoing project is.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
6
Complaints against the builder
0
Often reported per project on MahaRERA
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 30 Dec 2023 | 30 Dec 2027 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Strong track record
Tracking 2 projects — 0 delivered, 2 still active. Limited history — read the project list before drawing conclusions.
Official records
Builder: UDAY GHANSHYAM NAIK (NAME:UDAY GHANSHYAM NAIK)
Data last refreshed 21 Jun 2026.