Construction of 69 shops at sno 263 CTS no 6A/6 Ekta nagar Malwani Malad west Mumbai95
P51800000026
Behind schedule
This project is about 68 months past its latest deadline and is not yet marked completed.
Where this project stands
The journey from RERA registration to completion, in order.
Past deadline by ~68 months.
Registered with RERA
13 Jun 2017Original promised completion
31 Mar 2018The deadline the builder committed to at registration.
Revised deadline after extensions
30 Oct 2020Pushed back ~31 months across 1 extension.
Today — still not completed
About 68 months past the latest deadline.
Timeline & delay
Key dates and how they compare to what was promised.
13 Jun 2017
When the project was registered with RERA.
31 Mar 2018
The deadline committed to at registration.
30 Oct 2020
After all approved extensions.
—
Handover date, when available.
68 mo overdue67.7 mo
How far past deadline an ongoing project is.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
1
Complaints against the builder
0
Often reported per project on MahaRERA
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 31 Mar 2018 | 30 Oct 2020 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Good track record
Tracking 9 projects — 7 delivered, 2 still active. 3 of 9 (33%) ran late by an average of 3 months.
See MUMBAI HOUSING AND AREA DEVELOPMENT BOARD's full track record →
Official records
Builder: MUMBAI HOUSING AND AREA DEVELOPMENT BOARD (NAME:MUMBAI HOUSING AND AREA DEVELOPMENT BOARD)
Data last refreshed 21 Jun 2026.