KANAKIA PARIS
P51800000122
Delivered — but late
This project was completed about 27 months after its original promised deadline.
Where this project stands
The journey from RERA registration to completion, in order.
Completed.
Registered with RERA
5 Jul 2017Original promised completion
30 Sept 2019The deadline the builder committed to at registration.
Revised deadline after extensions
28 Dec 2021Pushed back ~27 months across 1 extension.
Marked completed on the portal
Shown as completed on the official registry (no exact date scraped).
Timeline & delay
Key dates and how they compare to what was promised.
5 Jul 2017
When the project was registered with RERA.
30 Sept 2019
The deadline committed to at registration.
28 Dec 2021
After all approved extensions.
—
Handover date, when available.
27 mo delay26.9 mo
How late the finished project was.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
11
Complaints against the builder
0
Often reported per project on MahaRERA
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 30 Sept 2019 | 28 Dec 2021 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Mixed track record
Tracking 7 projects — 7 delivered, 0 still active. 2 of 7 (29%) ran late by an average of 7 months.
See KANAKIA SPACES REALTY PRIVATE LIMITED's full track record →