KANAKIA SEVENS
P51800000388
Delivered on time
Marked completed on the registry on or before the promised deadline.
Where this project stands
The journey from RERA registration to completion, in order.
Completed.
Registered with RERA
15 Jul 2017Original promised completion
30 Dec 2021The deadline the builder committed to at registration.
Marked completed on the portal
Shown as completed on the official registry (no exact date scraped).
Timeline & delay
Key dates and how they compare to what was promised.
15 Jul 2017
When the project was registered with RERA.
30 Dec 2021
The deadline committed to at registration.
30 Dec 2021
After all approved extensions.
—
Handover date, when available.
On track0 mo
How far past deadline an ongoing project is.
0
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
17
Complaints against the builder
0
Often reported per project on MahaRERA
About the builder
How this developer has performed across all their tracked projects.
Mixed track record
Tracking 7 projects — 7 delivered, 0 still active. 2 of 7 (29%) ran late by an average of 7 months.
See KANAKIA SPACES REALTY PRIVATE LIMITED's full track record →
Official records
Builder: KANAKIA SPACES REALTY PRIVATE LIMITED (NAME:KANAKIA SPACES REALTY PRIVATE LIMITED)
Data last refreshed 21 Jun 2026.