PLATINUM TOWER - 1
P51800000487
Delivered — but late
This project was completed about 24 months after its original promised deadline.
Where this project stands
The journey from RERA registration to completion, in order.
Completed.
Registered with RERA
18 Jul 2017Original promised completion
31 Mar 2020The deadline the builder committed to at registration.
Revised deadline after extensions
30 Mar 2022Pushed back ~24 months across 1 extension.
Marked completed on the portal
Shown as completed on the official registry (no exact date scraped).
Timeline & delay
Key dates and how they compare to what was promised.
18 Jul 2017
When the project was registered with RERA.
31 Mar 2020
The deadline committed to at registration.
30 Mar 2022
After all approved extensions.
—
Handover date, when available.
24 mo delay24 mo
How late the finished project was.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
1
Complaints against the builder
0
Often reported per project on MahaRERA
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 31 Mar 2020 | 30 Mar 2022 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 1 project — 1 delivered, 0 still active. 1 of 1 (100%) ran late by an average of 24 months. Limited history — read the project list before drawing conclusions.
Official records
Builder: AKSHAY GRUHPRAVESH LLP (NAME:AKSHAY GRUHPRAVESH LLP)
Data last refreshed 21 Jun 2026.