EKTA TRIPOLIS PHASE II
P51800000731
Behind schedule
This project is about 6 months past its latest deadline and is not yet marked completed.
Where this project stands
The journey from RERA registration to completion, in order.
Past deadline by ~6 months.
Registered with RERA
23 Jul 2017Original promised completion
30 Jun 2022The deadline the builder committed to at registration.
Revised deadline after extensions
31 Dec 2025Pushed back ~42 months across 1 extension.
Today — still not completed
About 6 months past the latest deadline.
Timeline & delay
Key dates and how they compare to what was promised.
23 Jul 2017
When the project was registered with RERA.
30 Jun 2022
The deadline committed to at registration.
31 Dec 2025
After all approved extensions.
—
Handover date, when available.
6 mo overdue5.7 mo
How far past deadline an ongoing project is.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
19
Complaints against the builder
0
Often reported per project on MahaRERA
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 30 Jun 2022 | 31 Dec 2025 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 2 projects — 1 delivered, 1 still active. 2 of 2 (100%) ran late by an average of 30 months. Limited history — read the project list before drawing conclusions.
See EKTA EVERGLADE HOMES PRIVATE LIMITED's full track record →
Official records
Builder: EKTA EVERGLADE HOMES PRIVATE LIMITED (NAME:EKTA EVERGLADE HOMES PRIVATE LIMITED)
Data last refreshed 21 Jun 2026.