Atlanta Heights (A3) - 15th to 18th Floor
P51800000756
Behind schedule
This project is about 5 months past its latest deadline and is not yet marked completed.
Where this project stands
The journey from RERA registration to completion, in order.
Past deadline by ~5 months.
Registered with RERA
23 Jul 2017Original promised completion
30 Dec 2024The deadline the builder committed to at registration.
Revised deadline after extensions
4 Feb 2026Pushed back ~13 months across 1 extension.
Today — still not completed
About 5 months past the latest deadline.
Timeline & delay
Key dates and how they compare to what was promised.
23 Jul 2017
When the project was registered with RERA.
30 Dec 2024
The deadline committed to at registration.
4 Feb 2026
After all approved extensions.
—
Handover date, when available.
5 mo overdue4.6 mo
How far past deadline an ongoing project is.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
16
Complaints against the builder
0
Often reported per project on MahaRERA
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 30 Dec 2024 | 4 Feb 2026 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 16 projects — 4 delivered, 12 still active. 7 of 16 (44%) ran late by an average of 12 months.
Official records
Builder: Rare Townships Private Limited (NAME:Rare Townships Private Limited)
Data last refreshed 21 Jun 2026.